Set Budget Change Debit Account
Prerequisites
- Set the Project Budget Base. This includes the contract total cost value, budget baseline value, and budget set aside as management reserve.
- Enable the Change Control Log.
The following steps assume you have already enabled the control change log and you want to process control account and subordinate work package changes. The proposed budget change may be debiting or crediting undistributed budget or management reserve. Set the appropriate default budget account before you initiate the change control process in BOEMax.
- Select . The Manage Projects tab window displays.
- Click on the dropdown in the Ribbon Menu and select the project you want from the list.
- Select the Change Control tab.
- Set the to either or .
- Click in the Ribbon Menu.
- Optional. Close the Manage Projects tab.